How Are Paver Patios Installed Step by Step?

paver patio

A patio is not slabs on soil. Roughly half the labour and most of the skill sit below the surface, in work you will never see once the job is finished.

That is exactly why it gets cut. Nobody can inspect a sub base after the paving goes down, which makes it the easiest place to save money and the hardest place to get away with it long term. Almost every sunken, rocking or puddled patio traces back to one of the stages below being skipped or skimped.

This guide walks through how a patio should be built, covering both slab paving and block paving, with the specifications that matter and the point at each stage where cheap jobs take shortcuts. Written for Scottish conditions, where heavy clay and around 170 wet days a year make the groundworks matter more than they do in a drier climate.

Before anything starts

Two checks that shape the whole build.

Where the water will go. Every patio needs a fall built into it and a destination for the water. On clay, or anywhere water sits after rain, that usually means drainage going in before the patio does.

The damp proof course. The finished patio surface must sit at least 150mm below the DPC line on your house wall, or water can bridge into the brickwork and cause damp inside. This dictates the excavation depth, so it is established first, not discovered later.

Stage 1: Setting out

Marking the area accurately with string lines, pegs and spray paint. Levels are established from a fixed reference point, usually the DPC.

What should happen: the area is set out square, the finished level is calculated backwards from the DPC, and the fall is worked out before a spade goes in.

Where corners get cut: eyeballing it. Getting a patio square from a starting point that is rarely square is a real skill, and it shows up later in the cuts, the joints and the edges.

Stage 2: Excavation

Digging out to the depth required for the whole build up.

UseTypical excavation depth
Slab patio200mm to 300mm
Block paving, pedestrian200mm to 250mm
Block paving, driveway300mm to 400mm

The depth is not arbitrary. It is the sub base, plus the bedding layer, plus the thickness of the paving, measured down from the finished level.

What should happen: excavation to a consistent depth across the whole area, with the base of the dig already following the intended fall rather than being dug flat and corrected later.

Where corners get cut: digging 100mm instead of 250mm. A shallow dig forces a thin sub base, and a thin sub base is the single most common cause of patio failure. If you watch one stage, watch this one. Put a tape in the hole.

Stage 3: Spoil removal

Carting away the excavated material.

The volumes surprise people. A 40m² patio dug to 250mm produces roughly 10 cubic metres of soil and old material, which is several grab lorry loads.

What should happen: removed from site and disposed of legally, with the cost in the quote.

Where corners get cut: quoted as an exclusion buried on page two, or spread around the garden where it raises ground levels against the house, creating the damp problem described above.

Stage 4: Checking the subgrade

Looking at what has been exposed at the bottom of the dig.

What should happen: the exposed ground is assessed. Soft spots are dug out and replaced with compacted stone. Any made ground, buried rubble or peat is dealt with rather than built over.

Where corners get cut: building straight on top of whatever is there. A sub base over a soft spot settles at a different rate from the rest, and the paving above cracks along that line.

Stage 5: Geotextile membrane

A permeable fabric laid between the subgrade and the stone.

What it does: stops the sub base stone migrating down into soft ground, and stops clay pushing up into the stone. Over time, without it, the two mix and the sub base loses its structure.

What should happen: laid across the full area with overlaps at the joins, particularly on clay.

Where corners get cut: omitted entirely. It is inexpensive, which makes leaving it out a small saving and a genuine long term weakness on clay.

Stage 6: Sub base

The structural layer. The part that actually carries the load.

UseCompacted sub base depth
Slab patio, pedestrian100mm to 150mm
Block paving, pedestrian100mm to 150mm
Block paving, driveway150mm to 250mm

Material: MOT Type 1, a crushed stone graded to a Department for Transport specification. It compacts to a hard, stable layer and does not move.

What should happen: the stone is laid and compacted in layers, typically no more than 75mm to 100mm at a time, each one passed over with a plate compactor until it stops moving. The compacted surface follows the fall.

Where corners get cut, in three ways:

  • Depth. 50mm instead of 150mm. Invisible, and the reason patios sink
  • Compaction in one go. A 150mm layer dumped and whacked once is not compacted through its full depth. It settles afterwards
  • Wrong material. Builders waste, crusher run of unknown grading, or whatever was already on site

This stage is where the biggest price differences between quotes live. If a quote does not name the sub base material and depth, ask.

Stage 7: Laying the paving

Where slab paving and block paving diverge properly.

Slab paving

What should happen:

  • Slabs are laid on a full mortar bed, a continuous layer of mortar across the entire underside, typically 30mm to 50mm thick
  • Porcelain and dense natural stone get a priming slurry painted onto the back of each slab first, which bonds the slab to the mortar
  • Each slab is set to level with a rubber mallet, checked against the string line and the fall
  • Cuts around edges, manholes and curves are made with a disc cutter, kept consistent

Where corners get cut:

Spot bedding, also called dot and dab: five blobs of mortar under each slab instead of a full bed. It is faster and uses far less mortar. It also leaves voids under every slab that fill with water, which freezes, expands, and cracks the slab. Slabs rock, joints open, and the patio fails.

Spot bedding is the second biggest shortcut after sub base depth. Ask directly whether a quote is full bed or dabs.

Skipping the priming slurry on porcelain. Porcelain is dense and non porous, so without a bonding coat the mortar never properly adheres and slabs lift later.

Block paving

What should happen:

  • A laying course of sharp sand, typically 30mm to 50mm, screeded level over the compacted sub base
  • Blocks laid to the chosen pattern, with herringbone used for driveways because the interlock resists vehicle movement far better than stretcher bond
  • Blocks laid tight, hand tight, not spaced
  • Edge restraints installed, usually concrete haunched kerbs or edging blocks

Where corners get cut:

  • Laying course too thick, which rucks and settles unevenly
  • Stretcher bond on a driveway, which allows creep
  • Edge restraints omitted, which lets the whole surface spread sideways

Stage 8: Falls and levels

A fall of around 1:80 is the usual target, meaning the surface drops 1 unit for every 80 travelled. Over a 4m patio that is a 50mm drop.

What should happen: the fall runs away from the house, toward a channel drain, a gully, or free draining ground. The fall is built in from the excavation stage onward rather than created in the bedding layer.

Where corners get cut: laying the patio dead level because it looks neater, or running the fall in whichever direction is convenient. A level patio holds water. A fall running toward the house is worse than no fall at all.

The cross fall matters too. Some sideways slope is fine for drainage, but too much makes furniture wobble and feels unsettling underfoot.

Stage 9: Edge restraint and haunching

Haunching is concrete placed against the outside edge of the paving, holding it in place.

What should happen: any edge not retained by a wall or kerb is haunched, so the paving cannot spread sideways.

Where corners get cut: omitted on the assumption that mortar will hold it. Without restraint, edges drop, the outer course moves, and joints open progressively from the perimeter inward.

Stage 10: Jointing

Filling the gaps between the units.

Slab paving options:

MethodNotes
Mortar pointingTraditional, durable, labour intensive. Can crack if the base moves
Resin jointing compoundBrushed in and watered. Flexible, resists weeds and washout. Common on porcelain

Block paving: dry kiln dried sand brushed into the joints, then the surface vibrated with a plate compactor over a protective mat so the sand works down and the blocks interlock. Topped up and repeated until the joints are full.

What should happen: joints filled completely, surface cleaned off before the compound cures.

Where corners get cut: joints not properly filled on block paving, which means the interlock never develops and individual blocks move. On slabs, cheap jointing compound that washes out within a couple of winters.

Stage 11: Finishing

  • Manhole and inspection covers adjusted to sit level with the new surface, or recessed trays fitted so paving can be set into them
  • Surface washed down
  • Falls checked by running water across the finished patio
  • Edges and cuts tidied

Where corners get cut: manhole covers left proud of the surface, which is a trip hazard and looks unfinished.

How long it takes

For a 30m² to 40m² patio with reasonable access.

StageTypical duration
Setting outHalf a day
Excavation and spoil removal1 to 2 days
Subgrade checks and membraneHalf a day
Sub base, laid and compacted in layers1 day
Laying2 to 3 days
Jointing, haunching and finishing1 day

Roughly a week with good access. Where material has to be barrowed through a narrow close or carried through the house, that can double, because labour is the largest cost in any patio build.

Mortar and concrete pause in hard frost, and saturated ground can stop machine work entirely for days, so winter builds are more likely to see dates move.

The quick check on your own quote

Nine things that should appear. A quote with none of them is not necessarily bad work, but it gives you nothing to compare.

  • Excavation depth, stated
  • Spoil removal, included
  • Geotextile membrane
  • Sub base material named and depth stated
  • Compacted in layers
  • Full mortar bed, not spot bedding
  • Priming slurry, where porcelain or dense stone is used
  • Fall stated, running away from the house
  • Haunching or a named edge restraint

And one question worth asking out loud: what sub base depth are you using, and why that depth? A specific, immediate answer is a good sign. Vagueness is the warning.

Frequently asked questions

How deep should a patio be excavated?

Typically 200mm to 300mm for a slab patio, deeper for block paving on a driveway. The depth is calculated from the finished level, allowing for the sub base, the bedding layer and the thickness of the paving, with the finished surface sitting at least 150mm below the damp proof course.

How thick should a patio sub base be?

100mm to 150mm compacted for a pedestrian patio, and 150mm to 250mm for a driveway. It should be laid and compacted in layers of no more than around 75mm to 100mm at a time, not dumped and whacked once.

What is spot bedding and why is it a problem?

Laying slabs on blobs of mortar rather than a full bed. It leaves voids underneath that fill with water, and the slabs rock, crack and lift over time. A full mortar bed across the whole underside is the correct method.

Does porcelain paving need a priming slurry?

Yes. Porcelain is dense and non porous, so without a bonding coat painted onto the back of each slab, the mortar will not adhere properly and slabs debond later. It should be specified on the quote.

What fall should a patio have?

Around 1:80, meaning the surface drops one unit for every eighty travelled, and it must run away from the house toward a drain, gully or free draining ground. A level patio holds water.

How long does it take to lay a patio?

Roughly a week for a 30m² to 40m² patio with reasonable access. Poor access, particularly where material must be carried through the house, can double that because everything is moved by hand.

What is the difference between laying slabs and block paving?

Slabs go on a full mortar bed and are jointed with mortar or resin. Blocks go on a screeded sand laying course, are laid tight, then vibrated with kiln dried sand brushed into the joints so they interlock. Block paving also relies on edge restraints to stop it spreading.

Why does my patio have puddles on it?

Either no fall was built in, the fall runs the wrong way, or the sub base has settled unevenly beneath it. The first two are laying errors and the third is usually inadequate sub base depth or compaction.

Can a patio be laid in winter in Scotland?

Largely yes, with pauses during hard frost for anything involving mortar or concrete. The bigger constraint is saturated ground, which can stop excavation and machine access for days at a time.

What it comes down to

Depth, compaction, bedding and fall. Get those four right and a patio lasts decades. Get any of them wrong and it fails within a few winters, and the only fix is lifting the lot and starting again.The frustrating part is that none of them are visible once the job is done. Which is why the questions get asked at quote stage, not afterwards.If you want a patio priced properly, with the sub base depth and bedding method written down so you can hold it against anyone else’s quote, we are happy to come out and look at the ground first. Nineteen years, family run, building gardens across Glasgow and the Central Belt.